Prestea Area Successfully Completes Rehabilitation Works on Auto Transformer

By |2022-10-30T13:17:38+00:00September 19th, 2022|News|

The Prestea Area maintenance team on August 29, 2022, successfully rehabilitated and commissioned one of the two Auto Transformers, 10T8, which was idle for about five years, due to a faulty Circuit Breaker 10T8K at the Prestea 225kV substation. In addition, two new circuit breakers, 10T8K and 10T8D, three new disconnect switches, 10T8K-K Pantograph,