Prestea Area Successfully Completes Rehabilitation Works on Auto Transformer
The Prestea Area maintenance team on August 29, 2022, successfully rehabilitated and commissioned one of the two Auto Transformers, 10T8, which was idle for about five years, due to a faulty Circuit Breaker 10T8K at the Prestea 225kV substation. In addition, two new circuit breakers, 10T8K and 10T8D, three new disconnect switches, 10T8K-K Pantograph,